The city of Battle Ground, located in the heart of Clark County, has emerged as a dynamic and vital center for the social, commercial, and service needs of the central and north Clark County region.  The city, with a population of 22,120 serves a much larger trade area of 80,000. Both the city and the surrounding area is experiencing rapid and continued growth.  By 2035, the city's population is projected to be 37,300.

State Routes 502 & 503 bisect the city at its commercial core. Each day, 52,000 vehicles pass through the intersection, which is performing below Level of Service Standards, and with growth, is trending to perform much lower in the future.

 

Congestion Relief Project

Over the last several years, the city, in conjunction with WSDOT and the community, has sought to develop a blueprint of traffic improvements. The resulting SR 502/503 Congestion Relief Project is a multi-phase plan to implement transportation infrastructure upgrades, increase levels of service, and improve overall safety at the intersection.

  • Easing the flow of traffic at a major bottleneck and reducing commute times will mean improvements to quality of life, well-being and safety for residents and businesses.
  • Improving the ability to effectively & efficiently move goods & services means more businesses will consider locating here.
  • Unlocking these impingements to potential residential and business growth also unlocks and optimizes the shared revenue generation potential of the city.


Project Phases, Costs, and Funding

PhaseProject PhaseCostStatus
1West 12th Avenue/SR 502 Signal Removal and NW 5th Way Extension$1,530,000  Complete (2018)
2West 8th Avenue/West Main Street Improvements$160,000  Complete (2020)
3SR 503/SR 502 Intersection Improvements$4,700,000  Scheduled for 2022
4West 15th Avenue/SR 502 Intersection Improvements$1,075,000  Scheduled for 2022
5NW 12th Avenue/NW 1st Street Improvements$920,000  Scheduled for 2022
6NW 5th Street Improvements$3,800,000  Projected for 2022

Total Project Cost$12,185,000  


Funding

Connecting Washington
$7,700.000  
Surface Transportation Block Grant
$2,000,000  
Total Funding
$9,700,000