15th Avenue/Main Street Improvements

Overview

This project will improve operations at the intersection by adding a second southbound left-turn lane, by adding flashing yellow signals in the eastbound and westbound directions, and lengthening the left turn pockets in the eastbound direction.

Funding

Preliminary Engineering (PE)$0$87,500$87,500
Right-of-Way (ROW)$0$345,000$345,000
Construction (CN)$0$862,000$862,000
PROJECT TOTAL$0$1,294,500$1,294,500


City Funds*State FundsPhase Total

*State Funds are being provided through the Washington State Department of Transportation   Connecting Washington Program

Project Timeline

Preliminary Engineering (PE)2020 - 1st Quarter2026 - 3rd Quarter
Right-of-Way (ROW) 2025 - 1st Quarter2026 -3rd Quarter
Construction (CN)2026 - 4th Quarter2027 - 2nd Quarter

*Yellow indicates current project phase.

Project Location