NW 5th Street

This project will provide alternate access to SR 503 for the students at Battle Ground High School and others who travel north so they can avoid the SR 503/SR 502 intersection. 

Project Schedule

Task20212022

1st Qtr2nd Qtr3rd Qtr4th Qtr1st Qtr2nd Qtr3rd Qtr4th Qtr
Preliminary Engineering







Right-Of-Way







Construction








Funding

PhaseState Funds*Needed FundingTotal
Preliminary Engineering$145,000$0$145,000
Right-Of-Way$755,000$0$755,000
Construction$415,000$2,485,000$2,900,000
TOTAL$1,315,000$2,485,000$3,800.000

*=State Funds are being provided through the Connecting Washington Program