Tukes Mountain Reservoir No. 6

Overview

The City is constructing a new 106-foot diameter, 2.5-million-gallon ground level welded steel potable water storage reservoir on Tukes Mountain.  The project will replace aging infrastructure, address seismic concerns, and expand the City's water storage capacity by 1.5 million gallons, placing the City well in advance of anticipated water storage needs 

Construction includes, but is not limited to, demolition and removal of three existing concrete reservoirs, site clearing and excavation including rock blasting and removal, on site water pipeline improvements, updated electrical and controls, and additional site improvements including newly paved access road, retaining walls and stormwater facilities.

Funding

This project is funded through a combination of City water funds ($800,000), American Recovery & Reinvestment Act (ARAA) funds ($3,150,000) American Recovery & Reinvestment Act (ARAA), and $1,249,500 from the U.S. Department of Commerce (DOC). 

Project Timeline

This project is currently in the construction phase.

Preliminary EngineeringStart2022 - 1st QuarterComplete2024 - 3rd Quarter
Right-of-WayStartN/ACompleteN/A
ConstructionStart2024 - 4th QuarterComplete2026 - 2nd Quarter*

*Estimate

Project Area

This project is located north of E. Main Street in an area known as Tukes Mountain, near NE 23rd Avenue. 