92nd Avenue Sewer Pump Station & Force Main Project

A new pump station will be constructed near the intersection of NE 92nd Avenue and W Main Street (SR 502), opening up approximately 595 acres, including 310 acres of employment lands on the west side of the city, for development. The project components include the construction of a new pump station and force main.

Preliminary Engineering $180,000$250,000$0$430,000
Right of Way$140,000$0$0$140,000
Construction$2,000,000$0$2,000,000$4,000,000
PROJECT TOTAL$2,320,000$250,000$2,000,000$4,570,000


City Funds*State Funds PE** State Funds CNPhase Total

*  State funds are provided through a WA State Department of Commerce Grant

**  This project was supported by a grant awarded by the US Department of the Treasury.  Points of view in this document are those of the author and do not necessarily represent the official position or policies of the US Department of the Treasury.   Grant funds are administered by the American Rescue Plan act, State and Local Fiscal Recovery Funds & Washington State Department of Commerce. 

This project is currently under construction.  

Preliminary Engineering2021 - 1st Quarter2024 - 1st Quarter
Right of Way2021 - 3rd Quarter2023 - 3rd Quarter
Construction2024 - 2nd Quarter2025 - 4th Quarter
Sewer Project Location