Utilities
Goals & Accomplishments
- Sustain, operate and maintain the City's sewer system and treatment facilities.
- Sustain, operate and maintain the City's sewer, water, drainage, parks and facilities.
- Sustain, operate and maintain the City's water facilities and systems to provide clean water to our customers
- Daily inspections and recording of flows at all Lift Stations
- Daily inspection of emergency generators at each station
- Continuous monitoring and cleaning of piping
- Upgraded telemetry at Public Works Operations center
- Removed debris and noxious weed from Sewage Lagoon
- Began lagoon maintenance program for sewer lagoon
- Installed groundwater monitoring wells for sewer lagoon
- Monitored waste water characteristics for design of proposed reuse plant
- Cleaned EQ Basin
- Air Relief inspection long Force Main Alignment
- Videotaped 10 miles of sewer main line
- Began recording sewer flows at all lift stations
- Rebuilt 2 sewer pumps
- Completed Pump Station #1 reconstruction and new grinder station
- Demolished Old Sewer Treatment Plant
- Completed Betts Bridge Force Main Improvements
- Continued sewer pipe link into GBA maintenance software
- Maintained drainage system above and below ground
- Inventoried all Public Detention Basins and swales
- Perform swale and detention maintenance
- Cleaned all drainage facilities 3-4 times per year
- Cleaned NW 20th Avenue and City owned property ditches
- Cleaned SE Grace Avenue/199th Street/East Main Street ditches
- Mapped entire storm system
- Purchase new equipment for storm pond maintenance
- Started input of storm system into GBA maintenance software
- Daily monitoring of the water system including wellhead checks that include flow documentation
- Daily emergency pumping equipment inspections and continuous operation of the chlorine injection system
- Daily monitoring of pumping operations and their relation to available storage and customer demand
- Weekly sampling and reports to the Department of Health with 100% compliance
- Meter change out program (100 meters replaced)
- Diamond cut and repaired valve cans on Main Street and Parkway Avenue (20)
- Inventoried and repaired all fire hydrants
- Began backflow prevention program with commercial and industrial customers
- Installed 7 new backflow prevention devices at city facilities and sewer lift stations
- Cleaned and inspected the inside of 2 reservoirs
- Completed leak detecting flyer for citizens
- Certified staff in Water Distribution Manager levels 1 and 3
- Certified staff in Cross Connection Specialist (CCS) and Backflow Assembly Testing (BAT)
|
2004 |
2005 |
2006 Estimate |
2007 Projection |
Clean Sewer Lines |
20,000 feet |
20,000 feet |
12,000 feet |
15,000 feet |
TV Sewer System |
25% |
25% |
25% |
25% |
9 Mile Force Main |
Pigged/Cleaned |
|
|
Pigged/Cleaned |
Gardner Force Main |
|
|
|
Pigged/Cleaned |
TV System |
0 |
0 |
0% |
10% |
Ditch maintenance |
500 hours |
362 hours |
3000 hours |
3000 hours |
Clean Detention Basins |
2 |
2 |
1600 |
2000 |
Clean Catch Basins |
Westside |
Eastside (200) |
Westside (250) |
Eastside (250) |
Replace Meters |
50 units |
50 units |
100 units |
100 units |
Inventory System |
15% |
15% |
25% |
25% |
Clean Valve Cans |
0 |
0 |
0 |
100 units |
Repair Valve Cans |
0 |
0 |
20 units |
100 units |
|
 |
|
|
 |
|